start date in production order in ecc & APO

Hi All

We convert  planned order to production order in APO.

I could see dinffrenec in start date in production order in ecc & APO

Any specific reason???

Thanks

Suren

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Dec 29, 2015 at 10:22 AM

    Hi,

    1)Please make sure that you have publication type maintained for inhouse production with "retransfer" option in /sapapo/cp1, /sapapo/cp3 transactions.

    2)Run CCR report and check if you are able to reconcile the date difference?

    3) Make sure that the operation data is consistent in the orders in ECC and APO system

    4) Check if the PDS / PPM is consistent with no data missing between ECC and APO system.

    The above points should help you solve the issue

    Thanks

    Gomathi