In our current configuration the Task List section on the planning tab does not allow adding a task list to a work order. Where in configuration can I change the fields in yellow below to become modifiable?

I have looked all over SPRO and just not seeing it.

Thanks so much for your time.

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

2 Answers

Peter Atkin Feb 06, 2017 at 11:57 AM
0

Elisa,

You cannot assign a task list from this screen.

Instead, in IW32 use menu path: Extras->Task List Selection

PeteA

Share
10 |10000 characters needed characters left characters exceeded
avatar image
Former Member Feb 06, 2017 at 06:56 PM
0

Perfect...thanx Peter...I was thinking there was some field selection in config I was missing.