on 12-16-2015 12:16 PM
Hi Vikash,
Please check the validity dates in the work center, Costing TAB.
Regards,
Senthilkumar SD
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi ,
Please verify cost center is added in work center created by you in CR02
Please check the validity dates of cost center and activity type.
Verify Cost center category in KS02 and KL02
Go with following path
1.Create Cost center KS01
2.Create Activity type KL01 and SE cost element for the activity type KA06
3.Assign the cost center to Activity type with rate in KP26
4.Create work center CR01 put the created cost center and activity type with formulas in costing tab
5,At last create the routing CA01
Regards
Prasad
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Vikash
Please check the Activity Types, price maintained in KP26 .
& Correct Cost Center assigned to the Work Center .
Br
Tallha
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Kindly maintain the activity type value in the cost center through Tcode KP26 . than try to change the same in work center CR01.
than create the routing CA01.
Thanks & Regards
Sandeep Kumar Praharaj
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Create a Cost center using T code - KS01.
Create an activity type using T code - KL01.
Assign the Rates for an activity type & cost center combination using T code KP26.
In the input screen of T code KP26, enter version as 0, from period 1 and to period as 12 and the Fiscal
Year as 2008, enter the cost center, activity type click on overview screen (F5) ---> enter the per hour Rate
Under Fixed price and set value as 2 for distribution key and plan price indicator as 3.
After performing this, while creating the work center, this combination of activity type & cost center
Should be assigned. Then while creating routing/task list this work center can assigned for performing Operations.
Amit
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Vikash,
Can you double check your WC costing tab activities and cost center and for same combination you have maintained values in KP26?
BR
KK
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.