Im creating a Qualitative MIC in which I m getting a box to enter Assigned Inspection Cataloges.

As Im new qm guy - im stuck at this, not able to get clear data reg the error in SCN.

Please let me know how to proceed further

Refer the attached image.

Thanks

Mudassar

Accepted Solutions (0)

Answers (2)

Answers (2)

jogeswararao_kavala
Active Contributor
0 Kudos

Mudassar,

First you need to create a Inspectionn plan (QP01) for your Material. Here in the Inspection plan there will be Tasklist having different Operations. After this when you create an Inspection lot (QA01) on that material you will not get that error message you are getting presently, because this material is already having an Inspection plan.

Former Member
0 Kudos

Sir,

I have already created inspection plan for that material with tasklist and updated MICs in it.

But - the created lot is not taking in that Inspection plan.

Thanks

anand_rao3
Active Contributor
0 Kudos

You need to be sure that you are using the appropriate usage in the inspection plan.

Anand

jogeswararao_kavala
Active Contributor
0 Kudos

You need to give details of Code Group/selected set you have created using QS51. This discussion might be of use to you to know how selected set is made of.

Former Member
0 Kudos

Mr.Rao,

I have alreasy created MIC and updated MM with QM inspection setup - however

When im creating an Inspection Plan for the material - getting below error

Kindly help

jogeswararao_kavala
Active Contributor
0 Kudos

You should have an entry in the spro settings shown below for Tasklist type Q and Material type HIBE.:

Former Member
0 Kudos

Sir,

it is ok now.

But the created lot is not getting assigned the inspection plan ?

What i hv missed ?

jogeswararao_kavala
Active Contributor
0 Kudos

Not understood.

Former Member
0 Kudos

I created a lot.

Error says - No inspection plan has been assigned.

I have created an Insp plan and saved for thr same mat.