Routing with multiple operations, message C7067

Former Member
0 Kudos

Hello,

I want to make a routing with 2 operations.

When I only add operation 1, there are no messages when created a produciton order in CO01.

When I only add operation 2, there are no messages when created a produciton order in CO01.

When I add operation 1 and operation 2, CO01 gives warning message C7067:

"Diagnosis: You have not maintained all standard values in the operations"

"Procedure: Maintain the standard values in the operation"

The warning shows 2 times, 1 time for operation activiey 0010 (operation 1) and 1 time for operation activity 0020 (operation 2)

I have maintained the standard values for the operations in CA02 in 100% the same as they were when I only added 1 operation.

Anyone knows how to fix this warning?

With kind regards.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

I found the thing that makes the difference:

If all operations are at the same work center: No message.

If 1 of the operations is at a different work center than the others: Message C7067 like stated above.

Who can help me with solving this?