on 12-15-2015 1:51 PM
Hello,
I want to make a routing with 2 operations.
When I only add operation 1, there are no messages when created a produciton order in CO01.
When I only add operation 2, there are no messages when created a produciton order in CO01.
When I add operation 1 and operation 2, CO01 gives warning message C7067:
"Diagnosis: You have not maintained all standard values in the operations"
"Procedure: Maintain the standard values in the operation"
The warning shows 2 times, 1 time for operation activiey 0010 (operation 1) and 1 time for operation activity 0020 (operation 2)
I have maintained the standard values for the operations in CA02 in 100% the same as they were when I only added 1 operation.
Anyone knows how to fix this warning?
With kind regards.
I found the thing that makes the difference:
If all operations are at the same work center: No message.
If 1 of the operations is at a different work center than the others: Message C7067 like stated above.
Who can help me with solving this?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
9 | |
5 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.