Hello,

I want to make a routing with 2 operations.

When I only add operation 1, there are no messages when created a produciton order in CO01.

When I only add operation 2, there are no messages when created a produciton order in CO01.

When I add operation 1 and operation 2, CO01 gives warning message C7067:

"Diagnosis: You have not maintained all standard values in the operations"

"Procedure: Maintain the standard values in the operation"

The warning shows 2 times, 1 time for operation activiey 0010 (operation 1) and 1 time for operation activity 0020 (operation 2)

I have maintained the standard values for the operations in CA02 in 100% the same as they were when I only added 1 operation.

Anyone knows how to fix this warning?

With kind regards.

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • author's profile photo Former Member
    Former Member
    Posted on Dec 15, 2015 at 02:22 PM

    I found the thing that makes the difference:

    If all operations are at the same work center: No message.

    If 1 of the operations is at a different work center than the others: Message C7067 like stated above.

    Who can help me with solving this?

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.