Skip to Content

Refurbishment order

Hi PM Guru,

for In-house refurbishment maintenance order,

when i try to issue the damaged material against the order, system ask me the serial number for damaged material, i have already assigned the serial number in order. can anybody guide me where I m wrong.

Payal gupta

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • Feb 06, 2017 at 11:55 AM

    Where in the order did you assign the serial number?

    PeteA

    Add comment
    10|10000 characters needed characters exceeded

  • Mar 01, 2017 at 12:21 PM

    Hello Payal,

    During good issue , i think t-code is MIGO , there is Detail data , one tab is serial number, there you need to put serial no for material to be issued to order .

    Add comment
    10|10000 characters needed characters exceeded

  • Mar 01, 2017 at 03:16 PM
    Add comment