  • Dec 09, 2015 at 12:07 PM

    Hello,

    Press F1 on each of these fields and you will find the SAP documentation about each of them.

    The start date is the delivery date - PDT (planned delivery date).

    The opening date is calculated by deducting also the opening period (in case it is defined).This means:

    Opening date = delivery date - PDT - opening period.

    Kind Regards,

    Mariano

    Add comment
    10|10000 characters needed characters exceeded

    • Hi Jeet,

      Opening Date = Delivery Date - Planned Delivery Time - Opening Period.

      The Opening Period can be defined in the Product Master, PP/DS tab.

      The Opening Date more or less defines the date in which the PurRqs should be converted into PchOrd.

      For example, in /SAPAPO/RRP7 transaction, the system will select orders with opening date <= current date for conversion.

      You can check F1 help on Product Master and /SAPAPO/RRP7 fields for more details.

      Regards,

      Tiago

  • Dec 28, 2015 at 08:16 AM

    If you have a T-lane for external procurement, the start date represents only the transit time.