Dear All,

We want to create Automatic snapshot based on user status/system status change at project definition level.

we are using standard program DPR_snapshot_create to create snapshot and we need to add status check for the same.

Input needed.

Thanks
Amit Dhar

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • Best Answer
    Posted on Dec 09, 2015 at 03:35 PM

    Dear Amit,

    you can use FM CRM_STATUS_READ to receive the status-information.

    Best regards,
    Judith

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Dec 09, 2015 at 03:44 PM

    Hi Amit,

    My explanation is based on ECC PS:

    This is a standard function, no extra programming is necessary. In the configuration you need to do the following:

    1) Create a Status profile, define user status as many as per your snapshot requirement

    2) Define Project Version profile and assign which status will take automatic versions. You need to couple the status and version number.

    Once your project changes its status, then the version (snapshot) will be taken automatically,

    Regards,

    Dave

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.