TSM: Track time over production stages

Hi experts,

I Setup a Scenario for Material A that cosnumes Material A.1 (with activated TSM).

TSM Scenario works fine within that production stage, means that Check-TSM-Activity hook on last Routing steps gives a warning for expired component.

Do I have the possibility to Keep TSM check over the next production stage (planned Material B that consumes Material A with TSM inside)?

Best regards,

Anke

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

2 Answers

  • Posted on Dec 07, 2015 at 04:15 PM

    Hi Anke,

    Your question boils down to the question whether CHECK_TSM_COMPONENTS hook can check all assembly levels. According to the current design, it cannot. It was discussed some time ago with Product Owners.

    You should either move that TSM component from sub-assembly BOM to the top-level BOM or define the sub-assembly Material as TSM too.

    Br, Alex.

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Dec 07, 2015 at 04:14 PM

    Anke

    As far as I know, the hook only checks immediate child components, not components assembled to subassemblies. So, yes Material B can check for TSM, but only on its direct purchased components.

    Stuart

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.