CM21 have problem; No capacity requirements were found in the evaluation period.

Dear expert,

I have some problem in CM21 system throw error message

No capacity requirements were found in the evaluation period

and

No work centers or orders were found

I already setting

1. Work Center

In header Capacity tab, 'Relevant to finite scheduling' is ticked and 'Long-term planning' is ticked

2. control key, i use standard PP01

3. configure OPJK

4. configure OPKP

5. configure OPU3

How I can solve this issue.

Thank you

E1.jpg (75.4 kB)
E2.jpg (63.2 kB)
E4.jpg (94.5 kB)
E5.jpg (125.8 kB)
E6.jpg (110.2 kB)
E7.jpg (113.5 kB)
Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • Posted on Dec 07, 2015 at 07:49 AM

    Hello,

    Please check CM01 that you have capacity load on your work center. Your control key should mark for capacity requirement and scheduling. In CM21/25 on header menu Setting--Click on Change time Profile , Check for Evaluation Period .

    Best Regards,

    R.Brahmankar

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Dec 07, 2015 at 02:30 PM

    Thanapong,

    If you checking load for Planned orders then did you run the MRP with Lead time scheduling if not re run the MRP with same parameter and check again.

    BR
    KK

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.