Use of Costing Variant Actual (PPP3) in Product Cost Collector

Dear Experts,

I have searched a lot for subjected issue but could not get the clarity. I am pretty clear about PREM (Preliminary Cost) and PPC1 (Standard Cost Estimate). I do not have any clue on Costing Variant Actual (PPP3). Queries are.

1. Use of Costing Variant Actual (PPP3)?

2. Where (in which step/transaction) does any calculation takes place with PPP3 (like PREM calculates value in KKF6N and PPC1 calculates value in CK11N and CK24/CK40N)?

3. Why is it called Costing Variant Actual (PPP3), how it brings value of Material, Activity Price and Overhead cost?

4. Where can we see the difference between PPP3, PREM, PPC1?

Please give clarity on above points. I would be thankful to you guys. Thanks in advance. 😊

Regards

Ruksana

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

3 Answers

  • Best Answer
    Posted on Dec 10, 2015 at 04:43 AM

    Hi Ruks

    Any Costing Variant is used for the purpose of Cost Calculation..

    1. You do Std cost / Inventory Cost Estimate in CK11N. Std SAP provides PPC1 for that

    2. You do Prelimary cost estimate for Production Orders, using PPP1 and for Cost Collectors using PREM.. In Prel Costing, you calculate the Planned cost for the Manufacturing cost object

    3. Then you do Simultaneous Costing, which is the accumulation of actual cost on the Cost Object (Prod order or Cost Collector).. You once again need a Costing Variant for this (PPP3).. This Costing Variant is assigned in the Order Type (PP01, RM01 or PI01), just like the Costing variant in 2

    In PPP3, the material price valuation strategy is set to "Prices as per Price Control". This makes sense because the posting in FI for RM consumption would happen based on the Price Control

    You can check settings in each individual costing variant.. there is no report that can show a comparison between them

    And lastly, the settings offered in PPC1, PPP1, PPP3, PREM are just for reference. Don't restrict yourself to those.. You can decide what you want and create a new costing variant accordingly.. The ones for Prel and Simul. costing you must assign in the order types

    Hope this clarifies

    Rgds

    Ajay M

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Dec 06, 2015 at 03:31 AM

    Hi Rusana

    First of all you should understand the concept and use of costing variant at different object level cost calculation as well as to calculate standard cost/plan cost.

    1. PPC1 is used when we calculate standard cost in CK11N/CK40N to update cost at costing view 2 in material master

    2. PREM is used when we calculate preliminary cost at Cost Collector level

    3. PPP3 is used to calculate actual cost at Cost collector that means when you post GI/Activity through Back Flash system calculate cost for actual posting based on PPP3

    Basically when we calculate standard cost at CK11N/CK40N no actual cost is required to be calculate..so only PPC1 is used to calculate Plan/Standard cost

    But when we are calculation object level costing always a preliminary cost is calculated..you may call it estimated cost of plan production qty and Actual cost for actual consumption of goods & activity.So 2 costing variant are used at every object level cost calculation.

    In your case..PREM for preliminary cost and PPP3 for Actual cost at cost collector level

    I think this will clarify your question

    Kamal

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Dec 07, 2015 at 03:01 PM

    Dear Experts,

    Still I am waiting for my original questions. Please help.

    Regards

    Ruksana

    Add a comment
    10|10000 characters needed characters exceeded

    • Hi Ruksana

      When you post actual Goods Issue and Activity confirmation for Product cost collector through back flash (MFBF) system consider the setting in PPP3 to value the cost of consumption of goods issued and activity hrs to calculate actual cost of production.

      This variant is called actual because it calculate actual cost of goods issued and actual cost of activity confirmed.

      Diff between PREM and PPP3 is for repetitive manufacturing order at cost collector level

      PPC1 for standard cost calculation which is used to value GR level for SFG/FG product

      Kamal

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.