Hi, I am in the process of doing a migration from Classic RE to REFX and was wondering how will I go about changing the contract numbers for the new REFX contracts? Is it as simple as just defining the new number ranges and it is dealt with as part of the migration or would I need a program to change the numbers and put the old number in the Old Contract field?

Any thoughts or comments will be greatly appreciated!

Thanks

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Best Answer
    Posted on Dec 07, 2015 at 04:43 PM

    Hi CM,

    This is a purely business call.

    1. In one of my project, we kept the contract number range as external number and used the legacy contract number in the system. After migration, we once again changed the number to internal. When changing the number to internal, ensure that number range status should be the last contract number which is consumed during migration.

    2. In another experience, we kept the number range as internal and updated the legacy contract number in the new contract in the filed old contract.

    This should have been penned down during cutover strategy.

    Regards,

    Amar

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.