Skip to Content

Operation and split confirmation - Individual capacities

Hi Experts, appreciate if you could please clear some stuff here for me..

I have a requirement to work with operation splits. Just to keep it simple, I will take a easy example

Lets say I have an operation 0010 and I created just 1 split for this because I just have one individual capacity.

operation 0010 - start date dec 1 and end date dec 2

capacity requirements generated = 48 hrs

I created a split

split 1 - start date dec 3

capacity requirements = 48 hrs

if I dispatch operation 0010, it consumes 48 hrs of the capacity from dec 1 to dec 2

If I dispatch split 1, it consumes 48 hrs of the capacity from dec 3 to dec 4

but my real capacity is just 48 hrs, in the above example I am filling up 2 * 48 hrs which is incorrect, because for other production order, the capacity will be shown as overload..

so where am I am wrong conceptually?

Add a comment
10|10000 characters needed characters exceeded

Related questions

4 Answers

  • Posted on Dec 04, 2015 at 09:48 AM

    Hello,

    System displays the actual number of splittings on the operation detail view "Splitting". please check.

    If the number of splittings entered does not match the number of the individual capacities stored in the work center of the operation for the capacity relevant to scheduling, the system uses the smaller value of the two values for the calculation (Note 101308) - Number splittings during required splitting

    Best Regards,

    R.Brahmankar

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Dec 04, 2015 at 05:31 AM

    Hello Swathi,

    Please follow the below thread

    http://scn.sap.com/thread/3803064

    I hope this will help you.

    Regards,

    Amit Sharma

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Dec 04, 2015 at 02:01 PM

    Bharamankar and Amit.. Let me try to be clear

    I understand that we can dispatch operation and also dispatch splits of the operation. I also understand that the dates of the split doesnt have to match with its corresponding operation as the system will not do the check (as per OSS notes and help).

    OSS note also says that we need to first dispatch operation and then dispatch splits. if I disptach operation on a date and then disptach split of that operation on a different date (as system allows to have 2 diff dates), isn't that incorrect? because the same work is being done on two different dates and I am blocking capacity on 2 different dates...

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Dec 05, 2015 at 04:26 PM

    any help

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.