cancel
Showing results for 
Search instead for 
Did you mean: 

Order scheduling on weekend

Former Member
0 Kudos

Hi Experts,

I have one issue on scheduling of production orders.

I am using stable forward scheduling heuristics  with production horizon of 10 days.

On weekend i.e. Sunday will be holiday. my requirement is  there should not  be a overlap of order between Saturday to Monday.

i.e. Order should finish on Saturday and  order should be scheduled on Monday . How to achieve this ?

Br,

Sriniwas

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

May you get few clue