on 12-01-2015 11:48 AM
Hi experts,
when you enter a PP-PI order over COR3 you can go to GoTo - Costs - Analysis.
Now I search for a TCode which will show me such a report for multiple PP-PI orders with the possibility to delect also for material within a time frame (e.g. 01.01.2015 - 30.01.2015).
Currently I think that there is no report like this.
Hopefully you have an idea without development.
MAny thanks in advance.
Best regards
Patrick
Hello,
Please check the report S_ALR_87012993 & S_ALR_87012995
Below is a similar thread,
Cost analysis for multiple orders-reg | SCN
Best Regards,
Ameya B.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks for the suggestion and it partially helped.
It’d be good also if by chance you can provide me with a report to where I can see the same breakdown by G/L Account but that shows also the Production Order tied to it.
I would like to see what are the Production Orders driving the balance in the XXXXXXX Account. I can see for 2-3 orders, but would like to see for 100 of them. I need to see what are the ones with a balance in that Account.
Please suggest.
User | Count |
---|---|
85 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.