Resource Management in PPM without assignment in HR Org structure

Former Member
0 Kudos

Hello Folks,

Is there a way to use the Resource Management functionality in Project Management for Resources that are not defined in HR Org. Structure (e.g.contractors).

From what I understand, it is a prerequisite to have the Resources defined in HR Org structure to bring them as BP in PPM to really use the Resource Management functionality.

Also, want to do the CATS reporting for them. So, does just creating standalone BPs in PPM suffice ?

Thanks

Accepted Solutions (0)

Answers (1)

Answers (1)

gerry_hodgins
Active Participant
0 Kudos

Hello

I think you will need to have defined the resourced in HR

When transferring data from HR to the PPM system does not work "out of box",

certain BAdIs needs to be implemented in order to achieve certain behaviours

Example  RPM_BUPA_ATTRIBUTES of BAdI HRALE00INB_DATA_READ

so your Resources will need to be defined first


Ger