MRP - strategy 40

Hi,

We are using strategy 40 but the customer order are not consuming the PIR. Please find the screen shots

Md04.JPG (60.7 kB)
Add a comment
10|10000 characters needed characters exceeded

Related questions

3 Answers

  • Best Answer
    Posted on Nov 19, 2015 at 09:30 AM

    Hello Sun,

    Could you please share your planning strategy 40 screen shot..

    similarly please confirm whether your sales order has requirement type as KEV or KSV in the sales order procurement tab..

    And get back what is the consumption type you are using and what are the consumption period you have maintained in the material master..

    Regards,

    Venkatesh..

    Add a comment
    10|10000 characters needed characters exceeded

    • Hello,

      As per your screen shot your sale order is in MTO segment

      Check the OVZI setting for item category XXX origin should be 0 i.e., from material master. and

      Check in material master have you assigned any MRP group?

      Check the Planning strategy group of your MRP group

      Please refer consulting note 47045 - Tip check list f. indep.reqs.reduc./consmptn probs.

      1715491 - Planned independent requirements consumption/reduction by sales order and delivery

      Best Regards,

      R.Brahmankar

  • Posted on Nov 19, 2015 at 03:55 PM

    Hello

    You are using planning strategy 40 but the sales order is under the sales order special stock. Strategy 40 is a make-to-stock strategy, so this sales order is obviously not using the correct requirement type for this strategy and the consumption will not happen.

    On the document Demand Management: FAQ and consulting notes you will find links to the demand management FAQ notes, where you can find the solution for this issue.

    Regards
    Caetano

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Nov 19, 2015 at 11:54 PM

    Hi Sun Riser,

    As was mentioned by Caetano the problem is the Requirement Type.

    In MD04 you can see that the system is planning this sales order as Make to Order (note that you have a Block for the sales order in MD04). Change the Requirement Type in your Sales Order (VA02 --> Procurement tab) and put KSV.

    You will see that the special session (blue lines) in MD04 for the sales order you will disappear, meaning that this will be a Make to Stock planning scenario.

    Now, in order to consume the PIR, as was also mentioned by another expert, you need to enter a backward and / or forward period consumption, following by the right consumption mode.

    Kind Regards,

    Mariano

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.