Hi experts,

We are using SAP PPM 6.0.

There are several decision points for the item.

I have created an item.

The issue here is that I have got stuck at one particular decision point where I cannot move this particular DP forward or backward.

Kindly suggest some solution.

Thanks and regards,

Sameer

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Nov 19, 2015 at 10:38 AM

    Hi Sameer,

    Could you specify more why you cannot move your DP forward or backward?

    the reason can be your DP status are not correct defined, but we need to understand more your technical problem

    Regards

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member Sameer Gudi

      Hi Sammer,

      yes you are right. In this case i would ask you to check the customization whether the Status of the decision Point is maintained as end Status and the Status Group is maintained as closed for that particular item type.

      Br,

      Ketan

  • Posted on Dec 09, 2015 at 10:45 PM

    Hi Sameer,

    This is what we did with one of our PPM items with similar symptom:

    • By accident, decision point(DP) of an item, that was active, became inactive (status field empty) and user could not move the DP in either direction. The DP in question was second of four DPs for the item.
    • Decided to update the item via utility program RPM_DX_ITEM
    • Downloaded the excel format for RPM_DX_ITEM
    • Filled in data in worksheets 'Item' and 'Decision Point' in the excel workbook as below:
      • In worksheet 'Item', filled-in values for all fields for the item (for which I have values). (for ex:if there was planned start date for the item already, filled-in the same value here). If you don't maintain the values, it may be possible that the existing values will get wiped out. PLEASE CHECK
      • In worksheet 'Decision Point', filled in the first and second DPs for the item with Decision ID, name, and status:
        • for first DP- status was as in /rpm/decision table
        • for second DP- its first status as per configuration
    • Saved the file
    • Ran the utility program with the above file, in 'change' mode and with 'Overwrite decision points'
    • The DP in question became 'active'

    Hope it helps,

    Thanks

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.