Hi Experts,

My user facing issue..Usre just created an annual leave referral request for XXXXX user  employee abcd ... Simon Free for 17/12/2015 in X-Portal.. he not able to see this in the worklist when I log on with test user (XXXX)..

I have follow below link and i assigned all roles to user even not able see worklit taks.

Authorizations and Roles - Business Process Management Security Guide - SAP Library

I am new to this .. could you please help me ?

Regards,

Reddy

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi Rohit,

Yesterday my user has created one task but that task was not displaying under uwl work-list.

I went and checked NWA-->configuration--->process and tasks-->process repository -->i went to relevant component (click the component) -->Detail of component-->under i am seeing Task definition(Name ZZX) and process definition(name XXX)--> here i have clicked the   task definition but its showing (last 24 hrs) the status "Ready"--->  Just now i checked in Process definition -- its showing the Status "In progress".

Could you please help me how to this process display in over UWL work list ?

Regards,

Reddy

ROHITGERA1
Participant
0 Kudos

Hi Reddy,

check the owner of the task. Open the task and in the below table check owner, once the owner is assigned to the task then you can able to see in UWL and you can manually assign the owner by click on nominate owner button in task.

Thanks,

Rohit

Former Member
0 Kudos

Hi Rohit,

Sorry to say...

Still i am facing same problem ...

Again today also user has created new leave request that work items also not displaying  in UWL list.  see the below attachment ...

I went to NWA then got to Operation management-->Process and tasks -->Manage Process-->and click the all running process--> here today no running process showing.

Again i went to Configuration Management-->Process And tasks--->Process repository -->List of components-->  and i have sleeted my relevant  DC--> under DC--- Detail of Components-->and Double click the process name-->Its open the new window -->but here today no running process showing..

Could you please help me ASAP... I am now to BPM...

ROHITGERA1
Participant
0 Kudos

Hi Reddy,

As you say the Process Instance is not there in Process Repository it means Web Service of BPM is not called Successfully, Please check the logs for Web Service is getting failed. And also tell from where you are calling the BPM web service like from WDJ.

Thanks,
Rohit

Former Member
0 Kudos

Hi Rohit,

How and Where we have to check web services logs?

BPM web services calling from WDJ...

Regards,

Reddy

ROHITGERA1
Participant
0 Kudos

Hi Reddy,

You can check the logs in nwa/logs and from view select System logs and trace after that apply the required filter. You wull surely get the logs if web service is getting failed from WDJ Screen.

Thanks,

Rohit

Former Member
0 Kudos

Hi Rohit,

I am facing other issue ....

after apply the leave request... the request its showing in NWA -->operation management-->process and task-->manage task--> here unable to nominate the task to user...

the nominate button was disable.. could you please help me ..

please find the attached screen shoot..

Regards,

venkat

ROHITGERA1
Participant
0 Kudos

Hi,

I think the issue is coming due to not having Role.

Assign the BPM_SuperAdmin Role to the user who is accessing nwa.

Regards,

Rohit Gera

ROHITGERA1
Participant
0 Kudos

Hi,

Please check the Process Instance in the Process Repository and chek the owner of the task in the Manage Task, there you will able to find the owner of the task.

Thanks,

Rohit Gera

Former Member
0 Kudos

Could you please guide me how to check this?

i am new to BPM

ROHITGERA1
Participant
0 Kudos

Hi,

Just follow the Following Steps:

1. Login to SAP nwa(Newtweaver Administrator by http://<host name>:<port number>/nwa) with   NWA Admin Role.

2. then go to Configuration->Processes and Tasks->Process Repository.

3. In Process Repository you can find the List of Component, Serach your component (BPM DC Name)  and go to Details of Component table and select your Process and open it by click.

4.Now you will redirect to the manage process window where you can find your respective Process Instance. Choose your Process and click on the Button "Show Related Task".

5.It will redirect you to manage Task Window and then select your task and click on owners tab in the "Details about task instance" Table. Here you will find the owner of the Task.

Hope it will help

Thanks,

Rohit

Former Member
0 Kudos

Hi Rohit,

The components and task are started its long back 2015 May this month  not started any taks and components.

what to do can you tell me ?

Regards,

Reddy

ROHITGERA1
Participant
0 Kudos