I am facing a question when signing-off a Corporate Organization in SAP GRC PC 10.0. If the Corporate Organization has been signed-off, then if an issue is received in the Work Inbox of the issue Owner, is the control frozen in the way that if the issue is solved the status of the control is not changed?

Thanks a lot,

Kind regards,

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member197694
Active Contributor
0 Kudos

Hello John,

check is there any sign off is pending for sub node organizations under corporate organization

Refer the table HRP5337 for sign of status

one of the reason for status not changed is time frame also.

Refer the table GRPCSIGNOFFPLAN

Did you get chance to check the document in below link