We are planning to implement SAP QM module in existing ERP systems with SD,MM,PP implemented modules.

Please Let me know how much size will be increased during the QM implementation?.

Is there any sap notes is available for estimating sizing requirement for QM module?

Thanks & Regards
Thiru

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Posted on Nov 12, 2015 at 09:58 AM

    Dear Elumalai,

    there is no separate space required for Quality management i.e. the package which you are using that only has all the functional modules like PP,QM,SD,MM,FICO

    By maintain the master data we can utilise the QM also

    Regards,

    Venkatesh..

    Add a comment
    10|10000 characters needed characters exceeded

    • I would suggest you do an experiment in a sandbox. I doubt very much you will find any such sizing guidelines except from possibly SAP directly.

      So configure your sandbox for the basic QM stuff.

      Add in say 5% of your data that you expect to load.

      Take sizing readings directly before and after your loads.

      Figure out the difference and multiple by 20, (if you load 5%. if you load 1% multiple by 100, etc..).

      Craig

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.