Hi Team,

     I have created a Planned Order in the APO system using the transaction /SAPAPO/RRP3. This Planned Order has a Resource visible in the "Resource" column. When I convert this Planned Order to a Process Order, the Resource for this Process Order is no longer visible in the "Resource" column.

Could you please help me in resolving this issue?

Thanks in advance for the help and for your time.

Thanks & Regards,

Srikanth.

Accepted Solutions (0)

Answers (2)

Answers (2)

0 Kudos

Hi Srikanth,

Make sure there is an active integration model for the Resource. If there is not, the operation will be filtered from APO once you convert the PlOrd into Process Order.

Regards,
Tiago

Former Member
0 Kudos

Hi Krovvi sri

Before converting to process order .check your  are planned order is in allocated status . Any Heuristics you are running for scheduling purpose after generating planned orders .

Regards

Virender