Resource in the Product View getting disappeared after converting Planned Order to Process Order

Hi Team,

I have created a Planned Order in the APO system using the transaction /SAPAPO/RRP3. This Planned Order has a Resource visible in the "Resource" column. When I convert this Planned Order to a Process Order, the Resource for this Process Order is no longer visible in the "Resource" column.

Could you please help me in resolving this issue?

Thanks in advance for the help and for your time.

Thanks & Regards,

Srikanth.

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Nov 11, 2015 at 07:03 AM

    Hi Krovvi sri

    Before converting to process order .check your are planned order is in allocated status . Any Heuristics you are running for scheduling purpose after generating planned orders .

    Regards

    Virender

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Nov 16, 2015 at 07:52 PM

    Hi Srikanth,

    Make sure there is an active integration model for the Resource. If there is not, the operation will be filtered from APO once you convert the PlOrd into Process Order.

    Regards,
    Tiago

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.