Different behaviour of MRP when running background and when running foreground

Former Member
0 Kudos

Good evening.

I am facing a strange situation regarding MRP: it shows different behavior when background than of when running foreground. To be more specific:

MRP runs at plant 2900. There is a Production Order for the finished material. When MRP runs in background (transaction MDBT, variant 2900,

image 1) it does not plan all BOM materials (material 120800323 for example, image 2). But, when I run MRP from withing MD04 (MD02)  procurement proposals are created (material 120070748 for example, image 3).

Has anyone of you come across this??? Any suggestions????

Thank you very much,

Nikos Giannopoulos

Image 1

Image 2

Image 3

Accepted Solutions (1)

Accepted Solutions (1)

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello

did you check if the planning file entry exists for this material on MD21?

ON MDBT, a material will be only planned if the planning file exists and the flags Netch or Netpl are set. On MD02, however, the planning file in not considered.

You can also check if there is any error on MD05.

BR

Caetano

Former Member
0 Kudos

Thank you very much Caetano!

You were correct, planning file entry was missing. To be honest, i never thought it could be this... And even though i am cheeking, i can not see why the planning file entry was not created... I will keep on checking.

Any way, MANY thanks!

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello

You may run transaction MDAB, in order to ensure that all the planning file entries will be created.

Regards

Caetano Almeida

Former Member
0 Kudos

Very good point Caetano.

Also, consistency check would be helpful...

Once again, many thanks!

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Thanks for the feedback. If the issue is solved, could you please close the thread? See the blog for details.

former_member193808
Active Contributor
0 Kudos

Dear Nikos,

Caetano has already cleared the issue. To add on that, whenever you schedule using MDBT, it's better to have one run with NEUPL as Processing key for the first time. Later on, you can change it to NETCH and it will auto-run as desired.

The difference is that,

NETCH : Planning will be done for materials, for which Planning file Entry is there

NEUPL : Planing will be done for all materials, irrespective of the planning file  entry. This will make an entry to planning file too.

So, the first run with NEUPL will give the necessary planning file entry. Then subsequent MDBT schedule with NETCH will run as desired.

Thanks

Prem

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi Nikos,

I am not sure what you are trying to say but looking at screen shot seems both materials are getting planned.

Can you please check the where used list CS15 for material 120136907 and see if this is in BOM of FG other than T15A14080.

If it is just in one BOM then looks OK to me.

Thanks

kishan

former_member193808
Active Contributor
0 Kudos

Hi,

Could you please share the MD02 screen as well ?

Thanks

Prem

Former Member
0 Kudos

Hello Prem!

Here you are!