Setup matrix influence on SNP capacity?

Dear all,

For experts on this topic probably an easy question.

In our scenario, the setup- groups/keys are configured in the PPDS PPM. Setup activity checkbox in the PPM is active.

Setup group maintainance is going to takes place for new articles. So the setup group or time is not derived from the ERP routing group.

Does SNP-buckets take this setup time in consideration? Or only the production consumption?

I want to be sure the SNP capacity is being affected (or not) by assigning the group to the PPM.

Many thanks for a helpful answer!

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • avatar image
    Former Member
    Nov 09, 2015 at 11:55 AM

    Hi

    If you want SNP capacity can be affected using Set up Matrix. It´s mainly used in SNP optimizer.

    Please find below the link explaining the detail procedure.

    http://help.sap.com/saphelp_ewm70/helpdata/en/47/fca2fd9fc4384be10000000a42189b/content.htm

    Please let us know if the respective information is useful to you.

    Thanks

    Amol