Automatic reschedule activity date when shift another activity

Hi Gurus,

I have trouble about shifting activity, i try to imitate function ms.project automatic reschedule.

Act                       Start                    Finish

Activity10             02.11.2015           03.11.2015

Activity20             04.11.2015           05.11.2015

Relation between activity FS, Activity 20 as successor.

I try to extend finish date activity10 through CJ2B to 10.11.2015.

why activity20 did not reschedule to 11.11.2015(Start)  12.11.2015(Finish)?

please can someone help me to give me solution, what should i do?

best regards,

michael a

nw para.png (26.5 kB)
nw 1.png (11.7 kB)
Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    Nov 06, 2015 at 02:55 PM

    You have selected "WBS determines the dates".  So the dates on the assigned WBS are passed down to the activities and they have to work within those dates.  Strange things can happen if the dates aren't aligned.

    Is there a reason you wan this?  Otherwise change to strict bottom up planning.

    I also usually use backwards scheduling as the finish date is more critical that the start date.

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Maria Terence

      thanks sir terence, its solve. I miss the setup work center. when i see your SS, I aware about my work center. thank you so much.

      best regards,

      michael