Automatic reschedule activity date when shift another activity

Hi Gurus,

I have trouble about shifting activity, i try to imitate function ms.project automatic reschedule.

Act Start Finish

Activity10 02.11.2015 03.11.2015

Activity20 04.11.2015 05.11.2015

Relation between activity FS, Activity 20 as successor.

I try to extend finish date activity10 through CJ2B to 10.11.2015.

why activity20 did not reschedule to 11.11.2015(Start) 12.11.2015(Finish)?

please can someone help me to give me solution, what should i do?

best regards,

michael a

nw para.png (26.5 kB)
nw 1.png (11.7 kB)
Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

1 Answer

  • Best Answer
    Posted on Nov 06, 2015 at 02:55 PM

    You have selected "WBS determines the dates". So the dates on the assigned WBS are passed down to the activities and they have to work within those dates. Strange things can happen if the dates aren't aligned.

    Is there a reason you wan this? Otherwise change to strict bottom up planning.

    I also usually use backwards scheduling as the finish date is more critical that the start date.

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.