Hi all

I have this problem: a customer manage sales scheduling agreement, for example item of 500 pieces

in MD04 i see -500

then the customer creates order from scheduling agreement. now in MD04 i see both

- 500 from scheduling agreement

- 500 form sale order

why??? I need that when the sale order from scheduling agreement is created, the row inMD04 referred to that item disappear.

how can obtain it?

regards

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Shila,

The functionality you seek is typically achieved by creating deliveries directly within the scheduling agreement, instead of creating an 'order-with-reference....'.

You may be able to achieve your requirement by use of delivery orders.

Scheduling Agreements with Delivery Orders - Scheduling Agreements for Component Suppliers (SD-SLS-O...

Best Regards,