Hi

We have issue in PPDS optimizer with respect to sequencing of Semi Finished and Finsihed Product planned orders. After PPDS optimizer run we see Semi Finished are scheduled after Finsihed products.

We use PPDS optimizer.First we convert SNP planned order to PPDS planned order.After that run PPDS optimizer.

Finsihed product availability is on 01/04/2016 whereas Semi Finished is available on 20/04/2016.

We are using dynamic pegging relationship. Kept 30days of Maximum Earliness of a Receipt and Maximum Lateness of a Receipt at Semi Finished Level. For Finsihed Product level 400 days.Also In FG level there is 10 days as GR time to capture the Quality Inspection activities.

Expectation is schdule first the Semi finished products and then finished product.

Is there way to restrict this kind of sequencing. Suppose if my Semi Finished is getting delayed it should postpone Finsihed Product as well using PPDS Optimizer.In optimizer profile I have not activiated the Ignore upstream orders and Do not consider subsequent orders.

We dont want to use fix pegging.Is there way to by using dynamic pegging reletionship.

Please let us know your views.

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • author's profile photo Former Member
    Former Member
    Posted on May 06, 2016 at 01:37 PM

    Dear Roshan,

    Have you found an answer to your questions? I am facing same problems and it seems to be a bit of a challenge ti figure out the solution.

    Thanks

    M.

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Aug 17, 2016 at 01:09 PM

    Hi all,

    Thank you for your valubale input. The issue is still valid. Bottom up heuristics are not an option since they are not fully finite. I'm trying different settings with worse or better results.

    However I'd like to find your opinion on note 532979. There is a statement:


    "The Optimizer does not work with stock.In particular, this means that it cannot use the stock curve to recognize shortages.It can only recognize violations of pegging relationships and display them as delays.It is therefore important to ensure that pegging is as complete as possible before optimization."


    How should I underatand this? Does PPDS optimizer consider stocks and therefore tries to minimize delays taking the stock into account or not at all?


    M.

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.