Multiple Counter Plan does not work

Hello Experts,

Created a multiple counter plan. with OR ( see the attached-1) .

Enter 10HR meter reading --> did the scheduling --> it created a maintenance call

completed the work order -->and entered another 10HR Measurement document.

expecting another maintenance call at 20 HR but it did not.

it gave the following error message. ( No further Maintenance calls attached. Msg IP716)

what can be the issue?

PS. Have not checked "Special function for maintenance planning" in config.

Thanks,

Raneetha.

MP-3.png (42.3 kB)
MP-3.png (42.3 kB)
MP-1.png (37.0 kB)
Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • Best Answer
    Posted on Nov 07, 2015 at 07:07 AM

    Dear,

    I can understand that, Hope you have activated check box"Completion requirement" in scheduling parameters.

    That`s the reason it is showing the message as "New scheduling record can only be supplemented here if the previous maintenance calls have been completed".

    Could you kindly check this in maintenance plan - scheduling parameters tab.?

    Regards,

    Pardhu

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Nov 04, 2015 at 06:03 PM

    Greetings Raneetha,

    To be sure:

    1) You entered another Measuring Document with another 10 H difference in plus?

    2) What are your Maintenance Plan Scheduling Parameters?

    3) What does it say under Call Algorithm for call #2?

    Add a comment
    10|10000 characters needed characters exceeded

    • Hi Raneetha,

      This looks like the Annual Estimate playing a vital role. What is the Annual estimate you have maintained in the counter.

      Additionally, I did a replication of your issue

      Annual Estimate = 3650

      Counters = 10 Hr / 1mon

      1. You have posted measurement document 10 hrs.

      2. System generated a call to save.

      3. You completed the first call

      4. You maintained another 10 hrs

      5. Going into IP10 and scheduling, system will show as below

      You will get a message as "No further maintenance calls attached"

      6. Now if you post 10 hrs

      7. Go to IP10, you can see below screen

      Now the second call is scheduled and save to call.

      This message appears to confirm there is no further calls available to schedule. I hope this will disappear if the "Special functions of maintenance planning"

      Regards

      Terence

      Capture.JPG (40.2 kB)
      Capture.JPG (47.8 kB)

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.