hello all

we are using a consignment process in MM and at the end of the process, we are settling the used material with transaction MRKO.

Our business is in need of some sort of release process such as strategy or workflow before the settlement and booking of the amounts

The problem is that MRKO settles and books the material immediately.

is there a way I can avoid the booking until it has been approved?

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

not solved: i will transfer the question to MM

Former Member
0 Kudos

is there a way I can have a report of usage of consignment material including the price?

former_member183424
Active Contributor
0 Kudos

There are no facility like that. You can only do a test run (display) before post. You may check flexible development.