PO delivery date auto adjustment

hi all, my user needs some kind of functionality in which the delivery date in PO gets reset up on final release of PO. or is there any way where delivery date in PO gets reset on LC opening date. please advice.

namrah --------------------------------------------------------------------------------

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • Nov 04, 2015 at 01:02 PM

    Reset to what date?

    Reset based on what info?

    this can't be any standard and not best practice either, it would screw up planning and the reliability,  and add a lot work to those who have made their mind before creating the requisition and expect the delivery on their desired date.

    Delays because of approval activities have to covered the the purchasing processing time

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Nov 05, 2015 at 04:35 AM

    Dear,

    Possible with customization only check with abaper

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Nov 05, 2015 at 12:19 PM

    Hi Namrah,


    Kindly find below message for your interim relief:


    Manual maintenance of data for planned delivery time can be classified in the system:

    1 . At vendor level


    2.  At Material level


    3.  At purchasing info record level


    Kindly note:

    1. By changing the planned delivery time will affect your procurement process.

    2. System always calculates the planned delivery time in calendar days not working days.


    For Planned Delivery Time Calculation:

    Using T_Code: WPDTC (Planned Delivery Time Calculation) - > Click 'expand' the tool bar.

    Menu path: SAP Menu->Logistics->Materials Management->Purchasing->Master Data->Planned Delivery Time Calculation


    1. Calculate the planned delivery time:

    To calculate the planned delivery time, the system pick ups the no.of days between the order being placed with the vendor and actual goods receipt for the combination of vendor,plant,material,purchasing organization and vendor subrange.

    2. Change the date of the planned delivery time:

       

    To keep manually maintained planned delivery time or replace it with the calculated planned delivery time. you can decide for each individual value in the master data for the vendor, material and purchasing info record.

    Regards,

    Vivek