PO delivery date auto adjustment

Former Member
0 Kudos

hi all, my user needs some kind of functionality in which the delivery date in PO gets reset up on final release of PO. or is there any way where delivery date in PO gets reset on LC opening date. please advice.

namrah --------------------------------------------------------------------------------

Accepted Solutions (0)

Answers (3)

Answers (3)

former_member183349
Active Participant
0 Kudos

Hi Namrah,


Kindly find below message for your interim relief:


Manual maintenance of data for planned delivery time can be classified in the system:

1 . At vendor level


2.  At Material level


3.  At purchasing info record level


Kindly note:

1. By changing the planned delivery time will affect your procurement process.

2. System always calculates the planned delivery time in calendar days not working days.


For Planned Delivery Time Calculation:

Using T_Code: WPDTC (Planned Delivery Time Calculation) - > Click 'expand' the tool bar.

Menu path: SAP Menu->Logistics->Materials Management->Purchasing->Master Data->Planned Delivery Time Calculation


1. Calculate the planned delivery time:

To calculate the planned delivery time, the system pick ups the no.of days between the order being placed with the vendor and actual goods receipt for the combination of vendor,plant,material,purchasing organization and vendor subrange.

2. Change the date of the planned delivery time:

   

To keep manually maintained planned delivery time or replace it with the calculated planned delivery time. you can decide for each individual value in the master data for the vendor, material and purchasing info record.

Regards,

Vivek

Former Member
0 Kudos

Dear,

Possible with customization only check with abaper

JL23
Active Contributor
0 Kudos

Reset to what date?

Reset based on what info?

this can't be any standard and not best practice either, it would screw up planning and the reliability,  and add a lot work to those who have made their mind before creating the requisition and expect the delivery on their desired date.

Delays because of approval activities have to covered the the purchasing processing time

Former Member
0 Kudos

thanks jurgen for your prompt response.

the delivery date should be reset to 30 days after LC openeing date. these 30 days are mentioned in "P. deliv.time" field in delivery tab in item detail of PO

any abaping is recomended for such a scenario. please advice.

namrah.

JL23
Active Contributor
0 Kudos

and in which field do you have the LC opening date to enable a Z-program to know where it has to start?

this "P. deliv.time" field is the planned delivery time like it is in the material master. When the requisition is created then this time from material master is used to determine the delivery date. and in your case you want turn this upside down and redetermine the delivery date because the buyers are always late.

kunal_ingale
Active Contributor
0 Kudos

Hello ,

from where you will get the LC opening date??

or you need 30 days from the final release?

if there is delay in releasing the Po then delay in delivery date which will surely screw up planning and may cause in material shortage in production.

this is not a good practice and the time for complete release should consider in the planed tim only.

Similar Question was asked by someone last week too.

thanks

kUnal

Former Member
0 Kudos

@ jurgen and kunal

we are planning to mention the LC opening date in the field "date prel.doc." in the Prelim.doc tab in import tab in PO header.

JL23
Active Contributor
0 Kudos

good, then you have already a good portion for your function spec that you have to give to your ABAPer.