Hi ,

Want to technical complete and close some Orders created and processed from last month , if it closed now will it be reflected in previous month ?

Thanks.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Nov 04, 2015 at 11:17 AM

    Hello,

    I assume when you asked if this will be reflected in previous months you are talking about the settlement and costing of the order.

    In this case, if you setup the technical completion to an order that is not impacting in previous months. The impact takes place when you run the settlement to your order. With the technical completion you are allowing to run the settlement to the order.. meaning that all the costs elements of the order will be sent following your settlement rules (in most of the cases you sent all the cost to a cost center). Now if you set the CLSD (close) status, then that order can not be settled anymore.