on 11-04-2015 9:40 AM
Hi Zeek,
The scheduling schema is linked via the workflow. You have to change the workflow to "find" the new process alias (PA):
1. check the PA definition in
2. change the workflow in
SPRO SAP - Implementation Guide
SCM Basis
Configurable Process Scheduling
Process Definition
-> Maintain Process
(Enter the "WS..." number as TASK and choose the active version, continue with F5
goto header data and properties you find the value for the scheduling schema:
Here you find the link to the scheduling schema "SCHEDL"...
So you should copy the workflow and change it to ZSCHEDL or modify your existing "link" for your z process alias...
Good Luck and best regards,
Michael
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
9 | |
4 | |
3 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.