PP order settlement Issue

Hello Experts,

Issue during settlement of PP order:


Order created on 30th oct-15 and confirmed by 30th October-15


TECO also done on 31st Oct only.


but while checking variance in KKS2 in period 7 (i.e. oct'15) order is not showing any variance

but if I m selecting period 8 i.e. November-15,  its showing variance values.

kindly suggest why this issue is coming

Regards

PK Sahu

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Nov 04, 2015 at 08:49 AM

    Hello,

    When did run variance calculation (T-code: KKS1, KKS2)?

    For determination of DLV and TECO status, please review SAP Note 530563.

    To fix this the variance calculation can be reversed in period 8 or it has to be executed again in period 7.

    To prevent this from happening please ensure proper sequencing of the period end transactions and ensure that the variance calculation can be executed in the current periods only by using the period lock (transaction OKP1).

    Best Regards,

    R.Brahmankar

    Add comment
    10|10000 characters needed characters exceeded

    • Hello,

      Did you refer the OSS note 530563?

      Tte relevant for status TECO is strored in database field AUFK-IDAT2. This is filled, as soon as status TECO is set on the orde. You need to do the TECO in period 7.

      Best Regards,

      R.Brahmankar