How to see the planned requirement and actual consumption of material in Process order?

Hi SAP Guru,

In Process order, I can see the planned and actual quantity for material in COR2/COR3.

Is there a way to see the info for a bunch of process orders in order to see the variance?

Thank you,

Sally

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    Nov 04, 2015 at 01:36 AM

    Hi Sally,

    You can use COHVPI. Once you run the report, if you don't see both quantities, you can add more columns.

    Also note that this question should be moved to SAP PP space.

    Kind Regards,

    Mariano

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi Mariano.

      Thank you so much for your helpful reply.

      I did not find the PP bulliton board here so I chose APO instead.

      If possible please show me how to list all the forums here so I can put my question in the right place.