REM dep reqs requirement quantity not reduced when reporting pt backflush done

Hi Experts,

In REM, I have a planned order that has 2 reporting points. I have reported backflush on reporting point 1 for some quantity. the component quantity is good issued. but the requirement quantity for this component is not reduced in RESB of the planned order.

I found a note for this 459960. This note explains the behavior but it says sap doesnt have any solution for this.


my issue is when I run mrp after reporting point backflush, system thinks the component is still needed (because the requirement qty is unchanged) and orders more procurement proposals. in reality I have backflushed the component and I dont need them anymore.


what options do I have as a workaround?


Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    Nov 04, 2015 at 04:07 AM

    Hello SCM,

    Please check the below detail document for your issue

    Dependent requirement reduction after reporting point backflush

    I hope this information helpful to you.

    Regards

    Umesh Mali

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      That document just explains how dep reqs withdrawal quantity works..my issue is after rep point backflush, mrp does not respect the component withdrawal quantity..

      For example

      Comp requirement quantity is 10 for operation 1..i did rep pt backflush of op 1 and 10 quantity of comp consumed. When i run mrp system plans for 10 comp again.. but in reality it should not because i have consumed them and i dont need more.