on 11-03-2015 6:59 PM
Hi All,
We have Process Orchestration systems 7.31. We are trying to setting up the transport mechanism. We have individual SLD for each system.
First we are trying to define the transports from DEV to QA. For this we have two different SLD. Checked the documents and setup the transports groups. While importing ID objects from Dev to QA , we are receiving the following error.
"Obligatory transport target for business system not found in SLD"
Tried to configure as below
in both SLDs : Registered Dev, Qual PI/ECC systems in SLD as a Technical Systems and registered the same as business systems as PI-Business Systems are Integration server, ECC Systems are Application systems.
ECC: BS_DEV and BS_QA
PO : IE_PID, IE_PIQ
Defined 2 business system groups : DEV_TRANS and QA_TRANS.
Created transport target and source as below
For business system BS_DEV the transport target as BS_QA and for BS_QA source system as BS_DEV.
But when i do the import , we are getting the below error "Obligatory transport target for business system not found in SLD"
Please help us to resolve the issue.
Hi All,
Thanks for your valuble suggesstions. The issue is resolved after correcting the Registration of XI components within the SLD as per the OSS Note:
"1059576 - XI Directory import fails due to inconsistent SLD host names".
Now we are able to move the objects from Dev to QA. Once again thanks a lot for your time and help.
Regards
syam
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Try doing an SLD cache refresh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Try importing your BS_QA (which you might have already created in SLD) in ID first and then reimport the transport request once again.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi All,
Thanks for the suggesstions. I have tried all the suggesstions.
Created once again recreated the businsess systems and configured target transport systems.
Configured SLD synchronization between DEV and QA.
Now i can say both DEV and QA Business systems and PI systems in both SLD are same.
SLD cach refreshed.
SLD restarted.
Still the issue is not resolved. PI is unalbe to recongnise the Dev Buisiness system. It is giving error as " import failed because of buisnes system transfer of object integrated Cofiguration | MasterDataReplicationJMS|UOMFromTC_Aysnc_out|| : obligatory transport target for business system BS_DEV not found in system Landscape Direcotry"
Regards
Syam
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Sriram,
Thanks for the reply. Yes i checked the integration server assigned for each business system and also transport targets are maintained for integration server.
Please find the screenshots of the Developemtn SLD system . Since it is synchronzed with Qualitly system SLD. Same details will be available in Quality as well. Please let me know if you need any further details.
Development Business system
Development Target Transport
PI Integration Engiene details
PI Integration Engiene transpor target to PIQ quailty system
Hi,
Please confirm details in QA SLD..there can be a case of dev and qa sld being out of sync as well..as the issue is occuring while u trabsport to QA>..Can u pls check in QA SLD for Dev and QA business systems along with the integration server for dev and qa..Please provide the screen shots
Cheers,
Sriram
Hi Sriram,
Thanks again. As per my knowledge all the details are similar in Dev SLD.
Anyhow please find the QA SLD details below
QA SLD :
ECC Development Business System details
ECC Development Business system transport target details
PI Development System details
PI Development System transport target details
Quality ECC Business system details
Quality ECC Business System transport source
PI Quality system details
PI Quality system transport source details
Regards
Syam
Hi Syama sundar,
Apart from setting transport target in SLD for Dev and QA in QA SLD, also check if the integration server for PI selected in these business/technical system combination is correct INTEGRATION_SERVER_SID(For Dev and QA)
cheers,
Sriram
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Have you tried to configure SLD synchronization between DEV and QA? It should help with you issue and there will be no need to set up everything twice.
http://help.sap.com/saphelp_nw73/helpdata/en/48/c46668095735b6e10000000a42189d/content.htm
Regards,
Radek
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Just give this a try..
Open Integration Directory of QA
Import (Assign) the BS_QA into the ID(since its already created before transporting your request)
Then import your request
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
The error came because the business system BS_DEV and BS_QA are not properly configured to QA or SLD cache is not updated/clear in QA ID. Please check if the business system configuration in QA SLD is same as Dev and SLD cache is clear in ID.
regards,
Harish
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
87 | |
10 | |
10 | |
9 | |
7 | |
7 | |
6 | |
5 | |
4 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.