Dear experts,

Client is into assembly processing and we are done with the sales order cost estimate part. We dont have routing , overheads, variances  and not implementing product costing also.How to do costing for Finished goods? Please shed some light over this issue.

Cheers,

Hemanthkumar

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi...

You check whether you use Unit Cost Estimates for Sales Order Items through this SAP help portal(Unit Cost Estimates for Sales Order Items - Cost Object Controlling (CO-PC-OBJ) - SAP Library)

Hemanthkumar
Active Participant
0 Kudos

Hi Choi,

We have BOM but no routing, so quantity structure exists then in this scenario it is not possible to use Unit costing.Suggest the work around for this.

Cheers,

Hemanthkumar.

Former Member
0 Kudos

How is the raw material being valued?

Info record?

Planted cost in Material master?

In SPRO  there is Preliminary Costing and Order BOM Costing. Sales order costing has it's own Costing variants, costing types, etc.