Variant Config BOM not picked for Planned order error message 53

Friends,

I am facing the error, BOM not picked for a planned order of variant config sales order.

For the same values of the variant CU50 is checked & it mentioned Variant values are consitent and BOM picked w/o any issues.

where as in Planned order error message 53 appearing BOM not picked.

Please let me know, what additional details be checked for picking BOM correctly for the order

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • avatar image
    Former Member
    Nov 03, 2015 at 11:34 AM

    Hi,

    Hi Kumaran,

    Check the following:

    1. BOM Status - Valid Status is required.

    2. BOM Validity

    3. Lot size

    4. BOM Application marked for "Production Relevant".

    5. In OPL8, check same BOM application is maintained.

    Also try CO01 and check Component View for BOM picking.

    Did you checked same for another VC material's planned order.

    Assumed your CU50 is working fine.

    Regards,

    Dinesh Kumar V.

    Add comment
    10|10000 characters needed characters exceeded

  • Nov 04, 2015 at 06:49 AM

    Hello,

    What is the error message number?

    Refer KBA  1987762

    Check whether the header material and the BOM items from the BOM structure is a configurable material in the Material Master (transaction MM03):

    Material is marked as configurable on tab "Basic data 2".

    Plant-specific configuration is set on tab "MRP 3".

    Case 1:

    If the material is not configurable, but a configuration profile exists in transaction CU43, delete the configuration profile and run MRP again.

    Case 2:

    If the material is configurable, but it does not have a configuration profile, create one by using transaction CU41.

    Best Regards,