while transfering goods to subcontractor in 541 mvt type only one batch number is able to pick,for the other batch number it is not possible.

HI ,

when i was transferring goods with 541 mvt type with the batch management ,i am not able to send different batches of  a material,system is allowing only one batch number, please help me any one at the earliest

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • avatar image
    Former Member
    Nov 03, 2015 at 08:13 AM

    You need to have config for batch search strategy if you want multiple batches in 541..

    Add comment
    10|10000 characters needed characters exceeded

  • Nov 03, 2015 at 10:21 PM

    Does the material you are referring have stock available in MMBE ?