on 11-03-2015 5:47 AM
Hi Gurus
Hope that all are doing good.
My client business is on basis of MTS scenario.
He is getting monthly fix plan for production from customer, this fixed plan is closes every monthend.
It means If there is any open PR or PrdOrd it is NOT CARRY FORWARDED into next month.
I want to run MRP for current month only, irrelevant to the last month plan and open requirements.
kindly help me to drop open requirement from last month during the MRP run.
I have done some experiment using Firming and Roll forward days options. but I am not much clear about this.
Please help me on this, correct answer will be rewarded into points.
Your help will be valuable for me.
Thanks in advance
AKSHAY
SAP PP
Hi Guru,
Can u plz share the details of BAdi for the same
BR
Raj
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear gurus
Thank you so much for your help.
I will run the couple of scenarioes on this, and will close the discussion thread.
thnks once again
BR
Akshay
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Akshay,
I would say that you have to delete the unconsumed demand and delete the open orders form the previous months. You can delete the unconsumed demand with MD74/75/76 and delete the open production orders with COHV. The planned order and requisitions are going to be deleted automatically (except they are firmed).
Then before run the MRP or MPS, you will have to ensure you load the new demand (forecast).
Kind Regards,
Mariano
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
85 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.