How to plan considering Late Delivery Cost?

Hi Gurus!

We are trying to work with Late Deliver Cost or Maximum Late Delivery but we can't find any related Key Figure. ¿How can we work with this constraint in SAP S&OP?

Many thanks in advance!

Regards,

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • avatar image
    Former Member
    Nov 02, 2015 at 11:30 AM

    Hi Albert,

    You can use CONSDEMLATEDELIVCOSTRATE for late delivery cost rate or CONSDEMLATEDELIVMAX for maximum late delivery periods. More information is available in application help-

    Key Figures for Supply Planning - SAP Integrated Business Planning - SAP Library

    Thanks,

    Rohit

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Thanks Rohit..

      One more  key figure related to late demand fulfillment

      CONSDEMDELIVERED: Total Fulfilled Demand (Output of Supply Planning)

      See attached document for details. You can also find the key figures in SAP4 delivered model.

      Pramod