Dear Experts,
Is there any work around in SAP B1 to create amended PO.
Hi,
Which field you need to amend, Does the PO under the approval stages.
Thanks,
Kennedy
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Kennedy,
It's not under approval, need to change rate or qty.
But there will be a option to track the old PO and amended PO(after changes.
Ex:
First i created a 100qty*2500 price for PO No:10115.
Later updated the with120qty*2400price PO No:10115.
Just my customer want to track what was the qty and price before update.
Hi Bharathi Raja,
it's generally we used to do like that, but need to track the history.
You can use two methods.
1.If goods not received based on that PO, then you can update the PO manually
2.If goods received for one item, then create a new PO and add GRPO based on new PO and Old PO by using copy from option.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.