Edit CO11N confirmation activities without canceling whole confirmation stage

Dear Experts

Here I wanted to know whether is there any particular way to edit activity figures (in my case it is machine hours) at CO11N phase after completing the the production order (after good receipt of order) with out canceling the confirmation.

This requirement is there, specially when an user make a data entry figure error (please refer the attachment). Then we have to reverse all the data starting reversing production GR.

Please look into this matter.

Thank you

Esala 

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Nov 02, 2015 at 11:56 AM

    Hello,

    In standard SAPĀ  system will post the planned hours as actual hours during milestone operation confirmation.

    Refer OSS note 316462 - Incorrect activities from automatic confirmations

    Program ZPPCON_079 to correct the activities that have been posted incorrectly.

    Best Regards,

    R.Brahmankar