Dear Experts,

Is there any possibility in standard SAP to copy BOM changes from source plant to destination Plant.

Example :- BOM A is copied from Plant X to Plant Y. Later changes in the components, quantities of BOM A are done in Plant X and these changes need to be moved to Plant Y.

Do let me know if there is any option to (automatically) copy the BOM changes from one plant to another.

(Group BOM is not in scope for the customer, so please exclude any replies with Group BOM).


Thanks in advance,

Keerthi P.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Nov 02, 2015 at 08:33 AM

    Hello,

    There is no provision to copy changes of BOM from one plant to another without Group BOM in standard SAP.

    Best Regards,

    R.Brahmankar

    Add comment
    10|10000 characters needed characters exceeded

  • Nov 02, 2015 at 08:37 AM

    I think better options available could be CS01/or LSMW/BDC for creating the new material BOM(for the same material) in different plant.