on 10-29-2015 11:07 AM
Good day all of you,
I need your help concerning my case :
FING => this is the part that I will send to customer
COMPC =>is in the BOM of FING
DirtyC => This is the Dirty COMP, after production activity
I would like have after the DP (131) of FING have additional part known as DirtyC withe the same operation
COMPC + other parts =============> MFBF (131) =====> FING and DirtyC
For the rest of the story, we clean DirtyC and it's become COMPC again with a subcontracting activity. (For that no problem)
I don't know if it's possible, and for sure I don't know how the parameters it
Could you help me
Thanks in advance
Pierre
Hello Pierre
Did you try to insert DirtyC with a negative quantity on the BOM? In this case, system proposes a goods receipt for this material as a by-product.
BR
Caetano
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.