Skip to Content
avatar image
Former Member

Flexible planning- Transfer to Demand Management as proportios

Hi Gurus...

we have created a customized Info structure S9XXX with characteristics Sales Org, Product group/Material and Plant for consistent planning.

Update rules are also customized to pull a program and make specific calculations stored in 2 customized Key figures, also we have in this table the standard key figures that Standard SOP table(S076) has, Hierarchy and Planning Type were also created, when we create the planning with transaction MC93 and it is saved into an inactive version all information looks fine when we check it in SE16 (disaggregation by material based on Proportions calculated by historical data and written on Planning hierarchy)  .

The issue came up when we transfer this planning data to the Demand Management... as example:

In our customized info structure we have the materials A, B, C they belongs to a Product group.

A = 100 (in the key figure PRODU) that is the production plan we want to transfer.

B = 200

C = 200

Total(PRODU) = 500

What the system is transferring is the "Total" instead of the individual proportion quantities by material as is expected.

Can you please help me to understand if there is something I can do to fix it?

Regards.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Oct 29, 2015 at 10:29 AM

    Hi Francisco,

    Could you please share your MC81 and MC75 Screen shots

    for analysing the issue

    Regards,

    Venkatesh..

    Add comment
    10|10000 characters needed characters exceeded