on 10-28-2015 3:34 PM
Hi Experts
I want to change basic unit of measurement for material . since material does not have any transnational data it is not having any bom or routing . I have tried in mass also but not sucessfull
pls suggest .
Thanks & regards
Jaisree
Hi,
Changing the basic UOM is possible only on certain status as follows:
1. If there are no stocks in current and previous period.
2. If there are stocks in the previous period you can clear them as follows:
a) Post the stock in the previous period to the current period. E.g., Using Movement Type 561, so that the stock in the previous period is same as current period.
b) Clear the stock with the posting date in the previous period. E.g., Using movement Type 562.
3. No procurement element should exist e.g., NO PR, NO PO or Schedule Agreement or Production Order, Reservation etc. for the material.
Thanks With Regards,
Dinesh Kumar V.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Jaisree,
What's exactly happening? Are you getting any error message? Which one?
Anyway, there are some SAP notes regarding this topic, please check below:
138767 Changing the base unit of measure
95491 MM02: Error M3189 when changing base unit of measure
72046 Base unit of measure for material cannot be changed
30656 - Change base unit of measure/batch management requirement
Regards,
Marcelo
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
90 | |
8 | |
7 | |
4 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.