Material Staging - Auto to Manual

Hello All

We currently use LP12 to stage materials to a Production Supply Area (PSA) by grouping released production order quantities.

Now we want to activate manual staging from within a production order. Therefore, staging will now be processed by individual production order rather then a group of them.

My question is, which material staging indicator should I use?

Current control cycles are set to 3 - Release Order Part

Should I now change these to 4 - Manual staging? or 1 - Pick Part?

And should I now change from LP12 to LP10 as I will be picking for individual production orders?

Thanks in advance

Darren

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Best Answer
    Oct 29, 2015 at 05:56 AM

    Hi Darren,

    If you wish to pick the parts for each order separately, then use staging indicator 1 and use LP10.

    If there are some components needed very frequently and can be picked by the production guys by themselves, then you can activate manual staging with indicator 4 for these select few items. The way it works is warehouse supply in bulk for the manually staged materials and the production consumes the required quantity for the order.

    -Sushant

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      As you will be going to stage order wise you can use Pick list(I.e 1) control cycle for which you can stage through LP10.Also within that order if you want some materials to be stage in Bulk there you can assign Control Cycle 3 & stage those materials with LP12 as this material will not be seen in LP10.

  • Oct 28, 2015 at 06:02 PM

    for staging indicator which we should use and when. please have a look on the below thread                          

    http://scn.sap.com/thread/3683589