Skip to Content

MD11 planned orders with extra operations

Hi experts,

I have a scenario where i will get a route from an external planning system through PI, and sometimes the operations can be in different places, in that case a new operation - "TRANSPORT" has to be added between the actual operations.

Now upon receiving this data, a planned order has to be created with the extra operation, we have been trying to achieve it by using BAPI_PLANNEDORDER_CREATE, but are unable to insert the extra operation, the list of operations gets picked up from standard.

Can anybody help me with this.

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

1 Answer

  • Oct 28, 2015 at 12:39 PM

    There is no BAPI to insert a new operation on a planned order. In fact, planned orders will only have capacity requirements on table KBED and there is no actual operation, such as there is on a production order.

    BR
    Caetano

    Add comment
    10|10000 characters needed characters exceeded